Work package bill of quantities
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor), that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers to allow them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities:
- Elemental bill of quantities.
- Work package bill of quantities.
- Work section bill of quantities.
The work package breakdown structure undertakes measurement and description divided into employer, quantity surveyor or contractor defined work packages (based either on a specific-trade, or a single package comprising a number of different trades). This structure may be preferred by contractors for procuring from their supply chain.
NRM 2 suggests that a typical breakdown structure for a discrete work package might be:
- Bill No. 1: Main contractor’s preliminaries.
- Bill No. 2: Intrusive investigations.
- Bill No. 3: Demolition works.
- Bill No. 4: Groundworks.
- Bill No. 5: Piling.
- Bill No. 6: Concrete works.
- Bill No. 7: Roof coverings and roof drainage.
- Bill No. 8: External and internal structural walls.
- Bill No. 9: Cladding.
- Bill No. 10: Windows and external doors.
- Bill No. 11: Mastic.
- Bill No. 12: Non-structural walls and partitions.
- Bill No. 13: Joinery.
- Bill No. 14: Suspended ceilings.
- Bill No. 15: Architectural metalwork.
- Bill No. 16: Tiling.
- Bill No. 17: Painting and decorating.
- Bill No. 18: Floor coverings.
- Bill No. 19: Fittings, furnishings and equipment.
- Bill No. 20: Combined mechanical and electrical engineering services.
- Bill No. 21: Lifts and escalators.
- Bill No. 22: Facade access equipment.
- Bill No. 23: External works and drainage.
- Bill No. 24: Risks.
- Bill No. 25: Provisional sums.
- Bill No. 26: Credits.
- Bill No. 27: Daywork (Provisional).
[edit] Related articles on Designing Buildings
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Facade access equipment.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Schedule of rates.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Work section bill of quantities.
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.